CHP and District Heating Scheme
Main Contractor : F P Hurley & Sons Ltd
Contract Value :
£1.9 Million
Client : University of West of England
CHP and District Heating Scheme

Description :

Building on our success with the University of West of England, F P Hurley were appointed as Main Contractor to head up the CHP and District Heating Scheme. The project commenced on site in March 2019 and will take 22 weeks. The works include the supply, installation and commissioning of all heating plant and associated equipment within the Energy Centre, and supply and installation of substation integration equipment within each of the four existing buildings which connect to the network supplied by the Energy Centre,

Key elements of the work include the installation of two natural gas CHP units complete with exhaust system for the CHP units.

Two 35,000 Litre insulted thermal stores and heat network distribution pumps to be located within the Energy Centre.

Water treatment/filtration and pressurisation equipment to be installed within the Energy Centre.

Modification and supply installation of BMS systems within the Energy Centre and substations.

Supply and installation of all equipment to include heat exchangers, pipework, pumps, control valves and heat meters within the four substations to facilitate connection to the network.

Building works to allow for modifications to the existing plant room to create the Energy Centre, including new roof and access stairs.

 F P Hurley will provide an ‘as built’ 3D model of the completed installed works in BIM,


HVAC Installation(s) :

2 No CHP units, thermal stores, water filtration/pressurisation system, heat network distribution pumps, exhaust system, heat exchangers, heat meters, electrical installation, testing and commissioning, G59 Testing and certification, BIM model

FP Hurley & Sons Ltd